PROFESSIONAL DEVELOPMENT TIMELINE:
Much of the professional development conducted by the NFLRC has taken place when meeting with teachers over the course of initiating the TWI program and monitoring its implementation. The project coordinator also met with teachers many times over the school year to work on curriculum, strategies, and to discuss any other issues or concerns. The timeline below chronicles these visits and their respective purposes for the 2007-08 academic year.
Timeline of Work on Curriculum On Site in Two-way Immersion (TWI) Treatment Schools (2007-08 Academic Year):
Date |
Location |
Content |
| September 13, 2007 |
TWI Treatment School A |
TWI Project Coordinator Kaptain met with principal; met
with teachers all day. Discussed needs, curriculum, and materials/resources.
Discussed in detail the units developed for the year, planned activities in
conjunction with those units, and discussed the sequence of instruction for
the first unit. With kindergarten teachers, completed a concept map for the
first unit of the year. Discussed the differences in teaching phonics in
Spanish; need to focus on comprehension. |
| September 14, 2007 |
TWI Treatment School B |
Director Rosenbusch and TWI Project Coordinator Kaptain
visited new research site; met with principal, district ELL coordinator,
building ELL liaison, and visited TWI teachers’ classrooms. |
| November 1, 2007 |
TWI Treatment School B and other TWI school not in project |
Director Rosenbusch and TWI Project Coordinator Kaptain
met with principal; observed in classrooms. Met with TWI teachers over lunch,
as well as ESL teacher (future TWI teacher). Discussed characteristics of the program.Visited another TWI school in the district; met with all
TWI teachers after school to discuss SOPA and SOPA training planned for
March. |
| November 6, 2007 |
TWI Treatment School A |
TWI Project Coordinator Kaptain met with K and 1 teachers, also met for the first time the 2nd grade TWI teacher for next year. Discussed the units, began planning more
activities for individual units.Briefly met with district ESL coordinator and Director of
Equity concerning future of the grant and the program. |
| March 17, 2008 |
TWI Treatment School A |
TWI Project Coordinator Kaptain met with first grade
teachers about curriculum, and met with candidates for second grade TWI
teachers. Worked on units and concepts for second grade curriculum, developed
a new concept map. Discussed all materials and resources needed for next
year; began completing purchase orders/requisitions. |
| April 29, 2008 |
TWI Treatment School B |
Director Rosenbusch and TWI Project Coordinator Kaptain
administered SOPA. Met with teachers briefly to discuss student pairs,
results of the oral proficiency assessment. Discussed the
ELDA
and other measures used to evaluate student progress in Spanish and English. |
| April 30, 2008 |
TWI Treatment School A |
Director Rosenbusch and TWI Project Coordinator Kaptain
together with teacher trained in the SOPA administered SOPA. Discussed
ratings and results of the assessment. |
| May 16, 2008 |
TWI Treatment School A |
TWI Project Coordinator Kaptain and teachers trained in
the SOPA administered the SOPA to remaining pairs of students. |
| May 20, 2008 |
TWI Treatment School A |
TWI Project Coordinator Kaptain met with K, first, and
second grade teachers concerning curriculum and SOPA results. At second
grade, worked with teachers to further define the thematic units for next
year, identified materials and resources, and resolved questions and concerns
regarding the logistics of the program and schedule for next year. Discussed
with all teachers the methods used to teach reading; also discussed effective
strategies in the classroom to support cross-linguistic comparisons and
interlanguage reinforcement of concepts. |
|
|